Hearings Schedule Year-2019

Venue :- Court Room, UERC

S.No Title of the Case Date Time Petitioner/Respondent

Hearing in the matter of: Petition under Section 86(1)(e) and 86(1)(f) in respect of 10.5 MW Sarju-III Small Hydro Power Project of Uttar Bharat Hydro Power Pvt. Ltd.

11.10.2019 11:00 AM

M/s Utttar Bharat Hydro Power Pvt. Ltd. ….Petitioner

Uttarakhand Power Corporation Ltd. (UPCL) & Power Transmission Corporation of Uttarakhand Ltd. (PTCUL) …… Respondents

Hearing in the matter of: Dispute between M/s Bhilangana Hydro Power Ltd and Power Transmission Corporation of Uttarakhand Limited, relating to component A, that is, regarding to transmission charges for the use of intra-State transmission system for transmission of power from Bhilangana-III to Uttarakhand Power Corporation Ltd. through Tata Power Trading Company Ltd.

11.10.2019 11:00 AM

M/s Bhilangana Hydro Power Ltd. ….Petitioner

Power Transmission Corporation of Uttarakhand Ltd., (PTCUL) …… Respondents

Hearing in the matter of Application for adjudication of dispute between Beta Infratech Private Limited and UPCL in respect of termination of Power Purchase Agreement dated 01.03.2017 signed between Parties for Procurement of 107 MW of power on long term basis from 225 MW (ISO) Gas Based Combined Cycle Power Project in Village Mahuakhera Ganj, Kashipur, Distt. U.S. Nagar, Uttarakhand.

15.10.2019 11:00 AM

Sh. A.K. Jain, M/s Beta Infratech Pvt. Ltd. B-4/45, Safdarjung Enclave, New Delhi - 110029. (Petitioner)

Managing Director, Uttarakhand Power Corporation Ltd., Victoria Cross Vijeta Gabar Singh Bhawan, Kanwali Road, Dehradun. (Respondent)

Public Hearing in the matter of Application seeking approval for recovery of power purchase cost incurred in excess of the approved power purchase cost for FY 2018-19.

15.10.2019 11:00 AM

Managing Director, Uttarakhand Power Corporation Ltd., Victoria Cross Vijeta Gabar Singh Bhawan, Kanwali Road, Dehradun. (Petitioner)

& All the Stakeholders