Hearings Schedule Year-2021

Hearing Place :- UERC Hearing Hall,
Uttarakhand Electricity Regulatory Commission
"Vidyut Niyamak Bhawan"
Near I.S.B.T., P.O. Majra Dehradun (Uttarakhand)

Title of the Case Date Time Petitioner/Respondent

Hearing in the matter of Review Petition for review of the Order dated 11.06.2021 passed by the Commission in Petition No. 21 of 2020 in accordance with Section 94(f) of the Electricity Act, 2003 read with Section 114 & Order 47 of the Civil Procedure Code, 1908.

21.09.2021 11.30 AM

Sh. Digamber Singh Bisht, 1148, Indra Nagar Colony, Seemadwar, Dehradun-248006 .
                        ..............Petitioner
1. Managing Director, Uttarakhand Power Corporation Ltd., Victoria Cross Vijeta Gabar Singh Bhawan, Kanwali Road, Dehradun.
2. Shri Deepak Rawat, Director, Uttarakhand Renewable Energy Development Agency (UREDA) Urja Park Campus, Industrial Area, Patel Nagar, Dehradun
3. Sh. Dhirendra Singh Rawat, Village - Odda, P.O. Khandusain, Block - Kot, Distt. Pauri Garhwal                         ...............Respondents

Petition to Hon’ble Commission for resolution of matter pertaining to Deviation Settlement Mechanism (“DSM”) Claim for 214 MW (225 MW ISO) for Phase I of 2x225 MW (450 MW ISO) Gas Based Combined Cycle Power Plant at Kashipur, Uttarakhand to be filed by Sravanthi Energy Pvt. Ltd. under Section 86 of the Electricity Act, 2003 read with Regulation 59 of the Uttarakhand Electricity Regulatory Commission (Conduct of Business) Regulations, 2014 and the Regulations 13 & 16 of UERC (Deviation Settlement Mechanism and Related Matters) Regulations, 2017.

06.10.2021 11.00 AM

M/s Sravanthi Energy Pvt. Ltd.
                        ..............Petitioner

1) SLDC
2) PTCUL
3) UPCL
                        ...............Respondents